South Side Roof Replacement Progress
December 2012 - ? 2013
4 December 2012
6 December 2012
7 December 2012
12 December 2012
The first of the old vents has been removed and the resultant hole patched.
13 December 2012
14 December 2012
17 December 2012
9 January 2013
11 January 2013
15 August 2013
19 August 2013
20 August 2013
22 August 2013
(Friday) 30 August 2013
At long last, the South Side Roof Replacement was completed today.
It took 317 man hours to complete. Except for a few scrapes, cuts, and
hammering of the wrong nail, no other injuries were incurred.

Many thanks to Ian Reesor for spearheading the project. And thanks
also to Ernie Killen, Allen Morris, Les Smith, and Bob Clattenburg for
helping with the grunt work. And a special thanks to Bonnie Morine for
providing nourishment when the work extended into the afternoons.